Services Provided: Asset Selection, Design Basis Memorandum and Detailed Engineering
Discipline(s): Mechanical, Structural, Civil, Process
Budget: $40M – 50M
Duration: 2 yr
Scope Summary
The client required additional dredging assets to transfer MFT between two tailings ponds. The additional assets were required to maintain site wide pond balance requirements. GN2 completed an asset selection study for new dredging assets suitable for use based on demanding service conditions. Infrastructure was added for two dredging assets to be operated simultaneously, increasing total capacity of the transfer system. By utilizing existing on-site equipment and materials, GN2 was able to provide opportunities for capital cost savings and schedule reduction.